Procedure To Request for Supply Of Electricity

  • Submit a formal application letter for service connection to the nearest Business Unit.
  • A new service form which outlines the terms and conditions for obtaining electricity shall be issued to the prospective customer.
  • The duly completed form is then evaluated and load assessment of the premises carried out by the New Service Officer.
  • The expected load of the premises is then measured against the percentage load of the nearest substation to the customer.
  • All customers have a right to transparent electricity billing.
  • Having fulfilled all requirements, the request is then approved by the approving authority.
  • The premises should be energized within 24 hours from the date of approval of the request and meter installed accordingly.
  • Unless otherwise agreed, all future electricity bills for the supply address shall be issued in the name of the customer.